Nestlé
Project Scope
Problem
Several factories in Thailand (2011), some already flooded and others threatened. Needed quickly assembly to be able to reassemble at another site as necessary.
Procedure
Helped client analyze optimal solutions and helped install on site.
Solution
In one case the system was installed in 0,7 meter deep water. Done through the use of a barge, lowering as sea cable.
Result/Benefits
Could reopen flooded factory three months earlier than other factories despite already being flooded.